IFA Global Markets
Timetable / Venue Access
| Periods | Dates | Time | Gates (PKW) | Pedestrian |
| Build Up | 01 September - 03 September 04 September | 07:00 - 22:00 07:00 - 18:00 Please note: Due to noise restrictions, it is not possible to load in past 22:00. | Gate 27 | |
Event Open Days | 05 - 07 September | 05 - 07 September: 7:00 - 18:00 (from Gates 7 / 9 /21, South Entrance)
| Gate 7 Gate 9 Gate 21 Gate 25 Gate 25 | Hub 27 Entrance, Jafféstraße North Entrance, Masurenallee South Entrance, Jafféstraße East Entrance, Messedamm City Cube Entrance, Messedamm City Cube Entrance, Jafféstraße Entrance Hall 9, Messedamm Entrance Hall 7, Messedamm (till 13:00) Entrance Hall 21, Masurenallee (till 13:00) |
| Breakdown | 07. September | 18:30 – 22:00 Please note that structural breakdwon is only permitted after 22:00. | Gate 7 Gate 9 Gate 21 Gate 25 | Hall 7, Messedamm Hall 21, Masurenallee |
| Breakdown | 08 - 09 September | 07:00 - 22:00 No extension to this deadline is possible. | Gate 7 Gate 9 Gate 21 Gate 25 | Hall 7, Messedamm Hall 21, Masurenallee Hub 27, Jafféstraße City Cube Entrance, Messedamm |
Entrance Map for Event Open Days
Shell - All-included stand
Furniture and Electrical Fittings Rental Form
For shell/ all-included stand exhibitor, if you would like to order additional items for your stand, please fill out the form above.
Submission Deadline:15 July 2026.
Late submission:
30% surcharge for orders received after 15 July 2026.
50% surcharge for orders received after 10 August 2026.
Space Only Stand
Stand Plan Approval for Non-Complex Stands
All stand construction that do not meet criteria for complex stands, fall under non-complex stands.
Please ensure you carefully review the following sections in full before submitting your stand plans:
Submission Process
1.Complete the stand plan approval form - Non-Complex Stands and attach ALL required documents.
2.Plans for non-complex stands will be reviewed and approved by the EEP Safety Team Limited. Email: tom@eepteam.com
3.After approval, you will receive a building permit notice. Please note that construction cannot begin without this notice.
Deadline
Non-Complex Plans: 13 July 2026. All information is to be submitted in English/German and include exhibiting company’s name and stand number.
Approval Fees
- The standard fee will be 205,01 EUR + VAT.
- The late fee will be 399,23 EUR + VAT.
The late fee will be triggered when the 6-week deadline (13 July 2026) before build is over. - The emergency on-site-fee will be 950,00 EUR + VAT (On-site from 01 September).
*A permission to build will not be issued without receiving this payment.